What we do

Challenge

The Ghent and Terneuzen port areas in Belgium and the Netherlands respectively, are of great economic importance. With three locks, the lock complex in Terneuzen provides access to these ports located on the Ghent-Terneuzen Canal and is a crucial link in the Seine-Scheldt connection.

Research into maritime access to the Canal Zone has shown that a capacity problem could hinder shipping, with problems regarding the size, availability and reliability of the passage anticipated. To combat this, a large New Lock is being built at the location of the existing Middle Lock (built in 1910). The New Lock will provide better access and a smoother flow of traffic from the Western Scheldt to the Ghent-Terneuzen Canal and beyond.

At 427 m long, 55 m wide and 16.44 m deep, the lock will become one of the largest in the world, similar in size to the locks in Antwerp, Amsterdam and Panama. The first ship is expected to pass through the New Lock in 2024. While under construction there must be as little disturbance as possible to shipping, road users and the surrounding area.

Solution

The design and construct contract, as well as a two-year maintenance contract for this enormous project, was awarded to the Dutch-Belgian consortium Sassevaart. As a member of Sassevaart, DEME is responsible for the wet and dry earthmoving works and dredging, the bank and bottom protection works and the Schependijk remediation. A staggering 10 million m³ of material has to be dredged and we started works in late 2018. 

Earthworks and dredging

In the earthworks and dredging scope, a total of about 10 million m³ of soil will be removed for the construction of the New Lock. Our activities include among other things:

  • Deepening the Terneuzen Westvoorhaven to -16.44 m NAP.
  • Alteration of the western harbour entrance of the Westvoorhaven.
  • Removal of the existing spits of land around the Middle Lock, which will be replaced.

We will use the removed soil within the project as much as possible, or it will be disposed of in an approved disposal site. We will also use some of the dredged soil as foreshore sand suppletion at Knokke (Belgium).

Bank and bottom protection

Bank and bottom protection will be applied around newly constructed quays, mooring arrangements and the New Lock itself. This bank and bottom protection consists primarily of ripraps, representing approximately 400,000 tonnes.

Remediation

Various contaminated sites have been established on the Schependijk. We have the responsibility to remediate this contaminated soil before the northern part of Schependijk was delivered prepared for construction and the southern part is excavated.

The extensive scope includes:

  • Design & construction of a new sea lock of 427 m x 55 m and water depth of NAP-16.44 m.
  • Installation of sea lock operating system, including preparatory works for future remote operation.
  • Demolition works of the existing ‘Middle lock’, and existing surrounding buildings.
  • Construction of the new operations building.
  • Construction of a new service port and service building.
  • Installation of guiding, standby and service facilities for the lock operation.
  • Adaptation of existing road network and site layout, including execution of two bascule bridges.
  • Dry excavation works and soil remediation works.
  • Demolition and reinstallation of scour & shore protection.
  • Adaptation to the primary and regional flood defence systems.
  • Deepening of inner harbour (from –11 to –14 m) and outer harbour (from –12 to –16.44 m).
  • Backfill of lock platforms at levels NAP +7.5 m and NAP +9.5 m.
  • Dredging works.
  • Lock maintenance for 2 years post completion.

Related jobs

All jobs